WELCOME TO PROJECT MONITORING AND INFORMATION SYSTEM
 
 
CONSOLIDATED REPORTS
line decor
 
 
 
 
 
 
 
MPIR (Multisector Project for Infrastructure Rehabilitation) Loan 2151-IND
Jammu Urban
  Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
Works Completed 39 316.347007091 321.2582075 96.36%
Works Under Execution 2 45.06080705 39.5609398 92.40%
Works under Tendering 0    
Works To Be Tendered 0    
Jammu Urban Consolidate 41 361.407814141 360.8191473 96.03%
Jammu Transport
  Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
Works Completed 10 170.23441891 183.1257363 82.47%
Works Under Execution 1 39.5786 38.8951883 83.38%
Works under Tendering 0    
Works To Be Tendered 0    
Jammu Transport Consolidate 11 209.81301891 222.0209246 82.67%
         
Jammu (Urban + Transport)
Jammu Region Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
  52 571.220833051 582.8400719 87.58%
Note: The Physical Progress is calculated on the basis on man hours in every contract and all work components and involves complex calculations.