WELCOME TO PROJECT MONITORING AND INFORMATION SYSTEM
CONSOLIDATED REPORTS
|
Home
| |
Kashmir
| |
Jammu
| |
Equipment
| |
Jammu and Kashmir
|
MPIR (Multisector Project for Infrastructure Rehabilitation) Loan 2151-IND
Jammu Urban
Number of Contracts
Cost (Crores)
Expenditure (Crores)
Physical Progress
Works Completed
39
316.347007091
321.2582075
96.36%
Works Under Execution
2
45.06080705
39.5609398
92.40%
Works under Tendering
0
Works To Be Tendered
0
Jammu Urban Consolidate
41
361.407814141
360.8191473
96.03%
Jammu Transport
Number of Contracts
Cost (Crores)
Expenditure (Crores)
Physical Progress
Works Completed
10
170.23441891
183.1257363
82.47%
Works Under Execution
1
39.5786
38.8951883
83.38%
Works under Tendering
0
Works To Be Tendered
0
Jammu Transport Consolidate
11
209.81301891
222.0209246
82.67%
Jammu (Urban + Transport)
Jammu Region
Number of Contracts
Cost (Crores)
Expenditure (Crores)
Physical Progress
52
571.220833051
582.8400719
87.58%
Note: The Physical Progress is calculated on the basis on man hours in every contract and all work components and involves complex calculations
.