WELCOME TO PROJECT MONITORING AND INFORMATION SYSTEM
CONSOLIDATED REPORTS
|
Home
| |
Kashmir
| |
Jammu
| |
Equipment
| |
Jammu and Kashmir
|
MPIR (Multisector Project for Infrastructure Rehabilitation) Loan 2151-IND
Jammu and Kashmir
Number of Contracts
Cost (Crores)
Expenditure (Crores)
Physical Progress
Works Completed
67
587.560564677
590.783748200001
94.17%
Works Under Execution
45
739.878998674
620.742146299999
73.12%
Works under Tendering
0
Works To Be Tendered
1
6
Total
113
1333.439563351
1211.5258945
80.08%
Note: The Physical Progress is calculated on the basis on man hours in every contract and all work components and involves complex calculations
.