WELCOME TO PROJECT MONITORING AND INFORMATION SYSTEM
 
 
CONSOLIDATED REPORTS
line decor
 
 
 
 
 
 
 
MPIR (Multisector Project for Infrastructure Rehabilitation) Loan 2151-IND
Kashmir Urban
  Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
Works Completed 11 250.25 229.1271987 60.92%
Works Under Execution 0 Not Applicable Here
Works under Tendering 0    
Works To Be Tendered 0    
Kashmir Urban Consolidate 11 250.25 229.1271987 60.92%
Kashmir Transport
  Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
Works Completed 45 561.5708155 564.951522 86.99%
Works Under Execution 1 2.1157 3.1243216 28.05%
Works under Tendering 0    
Works To Be Tendered 0    
Kashmir Transport Consolidate 46 563.6865155 568.0758436 86.39%
         
Kashmir (Urban + Transport)
Kashmir Region Number of Contracts Cost (Crores) Expenditure (Crores) Physical Progress
  57 813.9365155 797.2030423 82.31%
Note: The Physical Progress is calculated on the basis on man hours in every contract and all work components and involves complex calculations.