| MPIR (Multisector Project for Infrastructure Rehabilitation) Loan 2151-IND |
| Kashmir Urban |
| |
Number of Contracts |
Cost (Crores) |
Expenditure (Crores) |
Physical Progress |
| Works Completed |
11 |
250.25 |
229.1271987 |
60.92% |
| Works Under Execution |
0 |
|
|
Not Applicable Here |
| Works under Tendering |
0 |
|
|
|
| Works To Be Tendered |
0 |
|
|
|
| Kashmir Urban Consolidate |
11 |
250.25 |
229.1271987 |
60.92% |
Kashmir Transport |
| |
Number of Contracts |
Cost (Crores) |
Expenditure (Crores) |
Physical Progress |
| Works Completed |
45 |
561.5708155 |
564.951522 |
86.99% |
| Works Under Execution |
1 |
2.1157 |
3.1243216 |
28.05% |
| Works under Tendering |
0 |
|
|
|
| Works To Be Tendered |
0 |
|
|
|
| Kashmir Transport Consolidate |
46 |
563.6865155 |
568.0758436 |
86.39% |
| |
|
|
|
|
Kashmir (Urban + Transport) |
| Kashmir Region |
Number of Contracts |
Cost (Crores) |
Expenditure (Crores) |
Physical Progress |
| |
57 |
813.9365155 |
797.2030423 |
82.31% |
| Note: The Physical Progress is calculated on the basis on man hours in every contract and all work components and involves complex calculations. |