Criteria adopted for shortlisting sub-projects
under ERA
Before
sanctioning of any Loan Asian Development Bank (ADB) prepares an elaborate
document called Report and Recommendations of the President for Board of
Directors (RRP). This document in respect of Loan 2151-IND
(Multi-sector Infrastructure Rehabilitation Project) which was the first
stand-alone project with multi-sector infrastructure rehabilitation in J&K
State with multilateral funding lays down the procedure for selection of
sub-projects for execution as under:
1. In
each sector i.e. Urban and Transport, a few sample projects were selected for
detailed techno economic viability. The
team of experts subjected each of these samples to detailed due diligence on economic, environmental and social resettlement aspects. The
results of the appraisals were used to create a standard appraisal format for
expediting selection of other sub-projects on similar criteria.
2. In
Transport sector the following three road sub-projects were studied in detail:
i) Kazikund-Kulgam road in Anantnag District
ii) Humhama-Raithan–Arizol-Road in Budgam District
iii)
Kanikadal
Bridge in Srinagar District
3. Similarly
under the Urban sector the ADB worked with the State
on the appraisal of two sample projects. The first sample sub-project covered the Water Supply Rehabilitation in
Jammu of which there was a
pressing need. The second sub-project
under Urban sector dealt with rehabilitation of drainage
system in low lying area of Talab Tillo in
Jammu.
Similar exercise was done in respect of replacement of dilapidated water supply
Transmission in
Srinagar and rehabilitation of drainage
system in the sub-urban area of
Srinagar
City which faced heavy
water logging.
4. Repeating above exercise 130 sub-projects were
first identified throughout the State under Transport and Urban sectors for upgradation/rehabilitation but subsequently a re-assessment
was necessitated in December, 2007 due to 11 per cent slippage of Dollar exchange
rate, doubling of Works Contract Service Tax in the State w. e. f. 01-04-2007,
estimation of cost on account of shifting of utilities and allotment of
sub-projects at a higher cost than the Engineer’s estimate and other variation.
Some of the sub-projects were not found feasible on environmental and social
& resettlement issues. The list of sub-projects that could not be taken up
in MIRP (Loan 2151-IND) is enclosed as Annexure-A (54 sub-projects). The balance 76
sub-projects have been taken up for execution throughout the State (75 allotted
and 1 tendered).